(1) Before installation of filter components to conduct a comprehensive inspection, the inspection is complete parts is intact, if found missing, damaged or deformed for a candidate tidy before installation. (2) On the framework for a bag carefully examined every after sealing off if we find bending or burr, trimmed to refill bag. (3) Bag is individually checked for size, stitching is solid, if there is leaking, for the conversion and then jump to the wire attached to the frame, be sure to banding catchy reliable, can not leak. (4) Should use special pads framework interface between the porous filter bag, not leak after pressing plate. (5) Fixed injection tube, the injection holes should be aligned with the center of the venturi tube, dryer deviation should be within 2 millimeters. (6) Check the exhaust system is flexible, gearbox and bearings, etc. Are injected into the lubricant, screw machine whether the debris, ash valve inside card Have mixing phenomenon. Normal acknowledgment qualified only after the test operation. Installed base (7)The filter should be at the same level, it can be used as rough sheet steel pad level, to prevent dust deformation. (8)The door cover and filter inlet and outlet flange sealing gasket material shall ensure that no leaks. (9) Air bag, electromagnetic pulse valve connection gas blowing tube should be securely sealed, non-leakage phenomenon. (10) Air filters should be filled filter material (foam, cotton flower, etc.) equipped with a pressure indicating device and safety valve. (11) Pulse controller and electromagnetic pulse valve installation shall comply with the provisions of the product specification. (12) The entire filter should be determined after a comprehensive inspection without problems, and after the test run, the system can be put into use. (13) When filter input system, cleaning should be based on need, determine the width of the injection interval and period. And check the filter pressure loss and ash, the determination of the collection efficiency. (14) Filter pipes and ancillary equipment should be carefully paint, good anti-corrosion treatment.